June 22, 2021

How to secure interim payments in construction projects

Lawrence Pearce, specialist Construction Law solicitor at Holmes & Hills, discusses the issue of securing interim payments, in full, during the course of a construction project.

Interim payments in construction

Under Section 110(1) of the Housing Grants, Construction and Regeneration Act 1996 (the “Act”) every construction contract shall “(a) provide an adequate payment mechanism for determining what payments become due under the Contract, and when, and (b) provide for a final date for payment in relation to any sum which becomes due”.

If for whatever reason the construction contract fails to provide an ‘adequate payment mechanism’ then the Scheme for Construction Contacts (England and Wales) Regulations 1998 (the “Scheme”), shall apply as an implied term.

Despite payment being at the forefront of every main contractor’s mind, it is surprising how many contractors are unaware of the consequences of failing to serve the required notices under the Contract/Scheme and the risk of a “Smash and Grab” Adjudication. Equally, lots of sub-contractors do not know the options they have available to them if a contractor fails to pay on the Final Date for Payment and/or fails to issue a valid notice in respect of an interim payment. 

Broadly speaking, every contract should allow for the following:

Default Payment Mechanism Image 1

* Note - The Act provides that the contract must include a provision for either a payment application (upstream) or a payment notice (downstream), however, it does not specify that a contract requires both. Although, most contracts provide for both. 

The Default Payment Mechanism in respect of interim payments

If for whatever reason the contract fails to provide an ‘adequate payment mechanism’ then the Scheme applies, including the following payment mechanism:

Interim Default Payment Mechanism

These provisions not only apply to your typical main contractor/sub-contractor relationship but many construction related services under professional appointments such as Architects, Surveyors and Engineers.

Payment Notices in respect of interim payments in construction

In accordance with Section 110A the Act, the payer (main contractor) or specified person is required to give a Payment Notice specifying the sum the payer considers to be due and the basis for calculating that sum, no later than five days after the Due Date. This applies even if the sum to be paid is zero. So, what if the payer fails to issue a valid Payment Notice?

  1. If the Contract between the parties “permits or requires” the payee to notify the payer (i.e., an Application for Payment) this document shall take effect as the Payment Notice; or
  1. If the Contract does not “permit or require” then the payee may issue a ‘Default Payment Notice’ specifying the sum due at the Final Date for Payment.

Taking (1) above, which is the most common scenario, if the paying main contractor fails to give a Payment Notice, then the sum set out in the sub-contractor's Application for Payment must be paid by the Final Date for Payment, subject to any Pay Less Notice that is given.

Pay Less Notices in respect of interim payments in construction

Section 111(3) of the Act allows the payer to pay less than the notified sum, provided that the payer gives a notice setting out the sum they consider to be due on the date the Pay Less Notice is served and the basis on which it was calculated. The sum may be zero.

The Pay Less Notice must be served no later than the prescribed period before the Final Date for Payment. The parties are free to agree the prescribed period, failing which, the Scheme will be implied, and the Pay Less Notice must be served 7 days before the Final Date for Payment.

If the sub-contractor disagrees with the value of works and sum stipulated in the Pay Less Notice by the payer, there are a number of strategic options available, but it is recommended that specialist advice is sought from a construction solicitor as each option carries merit and risk.

The payer has not issued a Payment Notice or Pay Less Notice, what now?

If the payer (main contractor) fails to issue a valid Payment Notice or Pay Less Notice by the relevant date, then the full sum is due and payable on the Final Date for Payment without deduction. This is not a new development and this position has been well rehearsed in the Courts since the case of ISG v Seevic in 2014.

Conclusion

The Default Payment Mechanism and the validity of the relevant notices have been debated by the parties to construction contracts for nearly a decade. Whether or not a notice is valid and whether the full sum is due and payable at the Final Date for Payment will depend on numerous factors.

It is recommended that main contractors and sub-contractors seek specialist advice in advance of entering into a contract on a new project, to allow for advice on and negotiation of the terms of the contract and, in particular, terms relating to interim and final account payment. Very minor alterations to clauses can materially improve the position of payer or payee with implications for cash flow and risk.

As well as providing pre-contract advice, the Construction Team at Holmes & Hills Solicitors provides pragmatic and commercial legal advice during the course of a project in relation to payment matters, to minimise contractual risks and identify contractual opportunities surrounding interim payments. After all, cash is still king!

Get Expert Construction Law Advice

Call 01206 593933 and speak to Construction Law specialist, Lawrence Pearce.
Or send an email
Key Contact

Lawrence Pearce

Partner

lpp@holmes-hills.co.uk

View Profile

Receive the latest legal updates

Get important legal updates, news and opinion sent to you straight from our solicitors.
Sign Up

A Mackman Group collaboration - market research by Mackman Research | website design by Mackman

linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram